Saturday, June 19, 2010

Update Progress


    1. Solar panels arrived from Germany but are still hold back at the terminal since the panels were supposed to arrive on the 10 June instead of 16 June. So an extension letter for the PO indicating reasons of delay was issued to Bendahari to solve this matter. 
    2.  We set the safety belt in a fix position and combine the 2 front brake cables into one handle. We tested the brake so it can break simultaneously. Other components such as isolator (emergency stop button) and horn are also tested.The back wheel was changed to a new one and we replaced a new hub motor.  
     
      